Tallo Khare Khola Hydropower Project (11 MW)

Welcome Tallo Khare Khola Hydropower Project is being developed by Universal Power Company Ltd. The project is a Run-of-River type hydropower project with generating capacity of 11 MW. According to the prevailing rules and regulations, the proponent had acquired Electricity generation license from Ministry of Energy and concluded Power Purchase Agreement (PPA) with Nepal Electricity Authority NEA for 11 MW. The rate of energy as agreed in PPA is Rs. 8.40 for dry season (Poush to Chaitra) & Rs 4.80 for remaining month which is considered as wet month. The PPA rate increases by 3% each year up to 5 year. According to interconnection agreement concluded with NEA the project has to evacuate the generated power to the proposed 132KV substation at Singati, Dolakha District.

Salient Features of the Project

River Khare Khola Location Suri, Khare, Chankhu V.C.D., Dolakha District
Catchment Area 177.8 sq Km Design Discharge 10.1 m3/sec at Q40%
Gross Head 140.5 m Installed Capacity 11 MW
Length of Weir 18 m Size of Desender 2 Chamber each of 8.50 m (b) x 75 m (l)
Particle Size to be Settled 0.20 mm
Penstock Pipe 3349 m Power House Type Surface with Bed Cutting
Type of Turbine Francis, 2 units Generator Type Synchronous, 3 phase AC, 2 units
Total Energy 62,731,751 kWh
Transmission Line 5.3 Km, Single Circuit, 132KV Interconnection Point Singati 132Kv Substation

Recent News

Special General Meeting(Magh 11, 2074)

Special General Meeting Notice of Universal Power Company Limited.

View Notice

विद्युत उत्पादनको अनुमतिपत्र प्राप्त गरेको बारे

कसुवा खोला हाइड्रोपावर लिमिटेडले सङ्खुवासभा जिल्लामा अवस्थित कसुवा खोलामा ४५ मेगावाट क्षमताको कसुवा खोला जलविद्युत आयोजनाको लागि विद्युत विकास विभागबाट पौष ६, २०७४ मा विद्युत उत्पादनको अनुमतिपत्र प्राप्त गरेको छ । कसुवा खोला हाइड्रोपावर कम्पनीमा युनिभर्सल पावर कम्पनी लिमिटेडले लगानी गर्ने योजनामा छ ।

सर्वेक्षण अनुमतिपत्र प्राप्त गरेको बारे

यूनिभर्सल पावर कम्पनी लिमिटेडले सोलुखुम्बु जिल्लामा अवस्थित इङ्खु खोलामा २४.२२ मे.वा. क्षमताको माथिल्लो इङ्खु जलविद्युत आयोजनाको विद्युत उत्पादनको सर्वेक्षण अनुमतिपत्र मंसीर २५, २०७४ मा र मनाङ्ग जिल्लामा अवस्थित नार खोलामा ३१.७७ मे.वा. क्षमताको माथिल्लो नार जलविद्युत आयोजनाको विद्युत उत्पादनको सर्वेक्षण अनुमतिपत्र मंसीर १४, २०७४ मा प्राप्त गरेको छ ।

वार्षिक साधारणसभा सम्पन्न

यूनिभर्सल पावर कम्पनीको आर्थिक वर्ष ०७३।७४ को वार्षिक साधारणसभा मिति २०७४।०५।२९ गते सम्पन्न भएको छ ।

AGM Notice (Bhadra 29, 2074)

AGM Notice of Universal Power Company Limited.

View Notice

Key Achievements

Date Key Achievement
2069/10/22 The Power Purchase Agreement (PPA) was concluded for 8.26MW.
2070/03/16 Syndicated loan agreement was signed with Bank of Kathmandu Ltd. as lead bank and Kumari Bank Ltd., Laxmi Bank Ltd., Janata Bank Ltd., Sanima Bank Ltd., Machhapuchchere Bank Ltd. and Kailash Bikas Bank Ltd., as participating bank.
2071/02/25 Grid Connection Agreement was signed with Nepal Authority Electricity (NEA).
2071/03/09 Supplementary Initial Environment Examination was approved from Ministry of Energy.
2071/09/23 The Company acquired electricity generation license from Department of Electricity Development/Ministry of Energy.
2072/10/24 Contract is awarded to professional Network for Engineering Services Pvt. Ltd. Detail Engineering and construction supervision of the project.
2072/12/02 The Company acquired transmission line Survey License for the second time form Department of Electricity Development/Ministry of Energy.
2073/2/17 Additional 2.72MW Power Purchase Agreement (PPA) was concluded with Nepal Electricity Authority (NEA)
2073/4/19 Contract is awarded fabrication of Civil Headwork’s of the project.
2073/5/9 Contract is awarded for fabrication and election of Hydro mechanical gates and stop log of Project.
- Detailed Engineering Study was done by Pasphupati Energy Development Company (P) Ltd. in association with CEMAT Consultants (P) Ltd., Clean Energy Consultants (P) Ltd., Akara Engineers & Associates (P) Ltd. and R.K. Survey Company (P) Ltd.
- 99% of private land is acquired by the company for project development.
- For use of public land and forest area approval has been acquired from the Ministry of Forestry and contract is signed between UPCL and Department of National park and Wild life Construction.
- Staff quarter construction has been completed and quarter for consultant is almost complete.